Staff Quarter, Store House & Guard House Building at Inaruwa Substation

Khushbu Nirman Sewa Pvt. Ltd., as prime contractor, has successfully completed the Staff Quarter construction at Inaruwa Substation, Sunsari. This encompassed sanitary and electrical work within a total floor area of 549.78 m2 and a plinth area of 203.32 m2. The structure, an R.C.C. frame building with a plinth area of 1544.70 m2, stands as a testament to our commitment to delivering functional excellence and quality construction solutions.

  • Client

    Hetauda-Dhalkebar-Inaruwa 400kV Substation Expansion Project, NEA

  • Client

    Nepal-India Electricity Transmission and Trade Project, NEA

  • Location

    Inaruwa, Sunsari

  • Project status

    Completed

  • Year Completed

    2078/06/30 BS and 2078/06/30 respectively